Google Cloud London Outage Caused by Backup Power Configuration Error

A misconfigured power sensor caused a six-hour London cloud outage by failing to trigger backup generators, leading to widespread service disruption.

Google Cloud London Outage Caused by Backup Power Configuration Error

A six-hour service disruption in the London cloud region on October 20 was caused by a programmable logic controller (PLC) misconfiguration that prevented emergency generators from activating. The failure originated in the europe-west2-b availability zone following an external utility cable fault. During a scheduled maintenance period, the facility was operating on a single-feed configuration. The PLC, responsible for triggering backup power, was to monitor voltage on the utility side of an isolated circuit breaker rather than the building's internal power feed. Consequently, the controller detected residual voltage on the isolated line and failed to issue a start command to the generators when the primary feed collapsed.

As the facility’s uninterruptible power supply (UPS) batteries were designed only for short-term bridging, they depleted within minutes, resulting in a total power loss for the data hall. The outage triggered an automated failover process that redirected workloads to the remaining two availability zones in the London region. This sudden surge in traffic saturated capacity, causing secondary performance degradation, elevated latency, and API timeouts across the broader region. More than 35 core services, including compute, storage, and database platforms, were affected.

The incident impacted a wide range of institutional clients, including major financial services, judicial systems, and logistics providers. The scale of the disruption has prompted inquiries from regulators regarding concentration risk and the resilience of critical infrastructure hosted on third-party cloud platforms. In response, the provider has reconfigured the PLC logic to verify both undervoltage conditions and physical breaker positions, ensuring that generator activation is no longer dependent on a single sensing point. Future risk mitigation strategies will focus on enhancing the robustness of failover protocols during maintenance windows to prevent similar cascading regional impacts.