R&F Development faces $2.58m payout over Johor condo delays
Johor Bahru High Court awarded compensation to owners of 84 Princess Cove units after finding breaches tied to phased completion. R&F plans to appeal.

R&F Development Sdn Bhd was ordered to pay RM10.56 million ($2.58 million) to owners of 84 Princess Cove units in a Sep. 10 Johor Bahru High Court ruling, Channel NewsAsia reported Nov. 5.
The decision matters to cross-border property buyers because the court accepted claims over 84 units while rejecting claims involving another 39 units, according to the CNA report.
According to a draft court order seen by CNA, the dispute turned on R&F’s decision to divide Princess Cove’s original first phase into Phase 1A and Phase 1B. The court found R&F breached purchase agreements with buyers by making that change.
Buyers in blocks A1, A2 and A7 received keys on Oct. 25, 2017, while the original Phase 1 was completed in November 2018, CNA reported. The court treated November 2018 as the operative handover date for calculating late-delivery compensation.
Crystal Ng, a 49-year-old Singaporean claimant who has since sold her family’s unit, told CNA: “When we purchase a unit, we expect the developer to fulfill its obligation. So what should be an exciting milestone for us became a prolonged and painful ordeal.”
Late-delivery compensation ranged from about RM34,000 to RM196,000 per unit. Awards for delays to shared facilities ranged from RM6,900 to RM39,000, based on 10% a year of one-fifth of each unit’s purchase price.
The court also ordered R&F to refund maintenance charges, sinking-fund payments, which are reserves for building upkeep, and water deposits collected before Nov. 8, 2018.
Princess Cove is a residential and commercial development in Johor Bahru near the Johor-Singapore Causeway. Developed by China’s R&F Group, it has a 650-metre covered pedestrian bridge linking it to Johor Bahru’s Customs, Immigration and Quarantine complex, CNA reported.
The claims were part of a lawsuit with 145 named plaintiffs filed in 2019. Purchasers initially won a ruling in 2021 without a full trial, but R&F appealed successfully, leading to a 10-day trial that ended in 2024.
The court dismissed claims tied to 39 units because those buyers signed purchase agreements after R&F changed the building plans, lawyers involved in the case told CNA. Those buyers were ordered to pay RM10,000 in legal costs per unit to R&F.
R&F’s lawyer Josiah Tea told CNA the developer intends to appeal. Purchasers’ lawyer NG Vinod told CNA that clients whose claims were dismissed also intend to appeal.
More stories
- Germans oppose Ukraine aid as poll shows support slipping
- Kim Jong-un receives 10 envoys after constitutional shift
- Ukraine claims Libya strike sinks Russian naval corvette
- COP31 climate talks collapse over fossil fuels and funds
- Russian military faces 1,087 recorded suicides in Ukraine war
- US faces China, Russia in Africa minerals contest
- Israel coalition talks loom as rivals fall short of power
- Serbia, Georgia and Turkey face EU accession limits over alignment
- Turkey's OIC trade reaches $108bn in first nine months
- Mojtaba Khamenei warns US, Israel after meeting 3 commanders
Latest news
- Trump prepares tariffs on China and other major exporters
- New-car buyers pay record average $50,087 in October
- Banks face ECB reserve debate over liquidity and profits
- Investors see Anthropic debut gains fade below $83 a share
- Iraq orders federal control over Kurdish-area oilfields
- Nvidia shares retreat as AI rally cools before PCE data
- Macy’s parade faces balloon limits as storm winds approach