Skip to content
LATEST
Global Affairs

Malaysia imposes environmental conditions on 117 data centres

Prime Minister Anwar Ibrahim said companies accepted the requirements, while Johari Ghani warned growth must not disrupt power for existing industries.

Malaysia imposes environmental conditions on 117 data centres

Malaysia has environmental conditions in place for 117 approved data centres, 55 already operating, Prime Minister Anwar Ibrahim told reporters at a Nov. 4 event, according to The Straits Times.

The approvals carry a combined maximum electricity demand of about 23,500 megawatts upon completion, or about 201 megawatts per approved centre if spread evenly, according to Atlas360 calculations.

Anwar spoke after attending the Mantap Malaysia Bersama AI programme at Universiti Malaya. “Yes, these are the conditions imposed... and they have accepted,” he said, referring to companies involved in the data-centre projects, according to the report.

Investment, Trade and Industry Minister Johari Ghani said on Nov. 4 that data-centre development must not affect electricity supply to existing industries. He said the facilities are important infrastructure for emerging technologies, but their expansion should not interfere with the energy needs of current sectors.

Data centres are facilities that house computing equipment and can require large, steady supplies of electricity. The remaining 62 approved Malaysian projects are at different stages of planning and construction, based on the figures in the report.

The report did not specify the environmental conditions, name the companies covered or give a timetable for projects that are not yet operating. It referred to concerns over data-centre operations in Malaysia and linked the issue to public scrutiny of projects in Johor.

Source: News report, The Straits Times, Nov. 4, 2026